Installation Begins

in

Today, the solar panel installation step of the project began.  It is expected to take 4 days. The  team started to install the rails, which is the framework that will hold the panels and the wiring. Tomorrow, they are expected to complete this work, as well as the wiring. Thursday, the panels will be installed, with Friday as contingency.  

The rails will hold the panels about 13 cms above the roof. This will provide sufficient clearance from the vents as well as airspace for the circulation of air.